Market & Cost · BOQ PRO
Every bag, tonne and brick — priced with live city rates.
City rates
Floors
2
Finish grade
Total estimate
₹71.6 L₹1,990/Sq.Ft · 3,600 Sq.Ft
| Item | Qty | Unit | Rate | Amount |
|---|---|---|---|---|
| Structure | ₹20.3 L | |||
| Cement (OPC 53)bags | 1,440 | bags | ₹410 | ₹5.9 L |
| TMT steel (Fe 500D)tonnes | 13 | tonnes | ₹62,500 | ₹7.88 L |
| Sandcft | 6,480 | cft | ₹60 | ₹3.89 L |
| Aggregate (20 mm)cft | 4,860 | cft | ₹55 | ₹2.67 L |
| Masonry | ₹2.36 L | |||
| Bricksnos | 28,800 | nos | ₹8 | ₹2.36 L |
| Finishes | ₹15.1 L | |||
| Flooring & tilingsq ft | 4,680 | sq ft | ₹95 | ₹4.45 L |
| Paint & puttysq ft | 12,600 | sq ft | ₹28 | ₹3.53 L |
| Doors & windowssq ft | 648 | sq ft | ₹1,100 | ₹7.13 L |
| MEP | ₹9.36 L | |||
| Electrical (wiring & points)sq ft | 3,600 | sq ft | ₹140 | ₹5.04 L |
| Plumbing & sanitarysq ft | 3,600 | sq ft | ₹120 | ₹4.32 L |
| Labor | ₹24.5 L | |||
| Civil labor contractsq ft | 3,600 | sq ft | ₹420 | ₹15.1 L |
| Supervision, overheads & contractor margin% | 15 | % | ₹62,284 | ₹9.34 L |
Thumb-rule quantities for a framed structure at Delhi NCR rates. Use a structural engineer's BOQ for tendering.